08-26-16 Progress Notes

[Updated: March 13, 2023 | Published: August 26, 2016]

Our 16-unit Flats building is being framed with the other 3 buildings to follow. see construction update below photo.

Sitework & Utilities:

Perform permanent sanitary reroute now that city has signed re-design

Garages:

Clean up landscaping

Start irrigation, subcontract Award letter sign for Oakland Irrigation

RCC and Andy Howland to finalize trees with Darby Creek, release and get done

Utility Pump House/Entry Feature:

Metal roof, Gutters and downspouts

Pavilion:

Complete the carpentry trim work

Finish pavers, Irrigation, Landscaping

Flats:

Building 6772: Prep for exterior framing, CMU shafts

Building 6766: Pour first floor concrete topping, Prep for exterior framing

Building 6758: Continue CMU walls

Building 6741: Continue CMU walls

Riverstone:

Continue foundations

Start foundation walls

Upcoming Dates:

Mid-Sept, Water Meter Building complete

End-Aug, Pavilion substantial completion

Late Sept., Start PT/OT Renovation work at The Meadows

Late Sept., Start Friendship Community Center Lobby Renovation & B-Wing Office Renovation

 

 

News Categories

Get the Latest Email News

  • This field is for validation purposes and should be left unchanged.
Aa Aa Aa
THREE Fall Events in October and November! Click here for details and registration