[Updated: March 13, 2023 | Published: August 26, 2016]
Our 16-unit Flats building is being framed with the other 3 buildings to follow. see construction update below photo.
Sitework & Utilities:
Perform permanent sanitary reroute now that city has signed re-design
Garages:
Clean up landscaping
Start irrigation, subcontract Award letter sign for Oakland Irrigation
RCC and Andy Howland to finalize trees with Darby Creek, release and get done
Utility Pump House/Entry Feature:
Metal roof, Gutters and downspouts
Pavilion:
Complete the carpentry trim work
Finish pavers, Irrigation, Landscaping
Flats:
Building 6772: Prep for exterior framing, CMU shafts
Building 6766: Pour first floor concrete topping, Prep for exterior framing
Building 6758: Continue CMU walls
Building 6741: Continue CMU walls
Riverstone:
Continue foundations
Start foundation walls
Upcoming Dates:
Mid-Sept, Water Meter Building complete
End-Aug, Pavilion substantial completion
Late Sept., Start PT/OT Renovation work at The Meadows
Late Sept., Start Friendship Community Center Lobby Renovation & B-Wing Office Renovation