[Updated: August 2, 2018 | Published: July 11, 2017]
The days before the Flats residents move in are flying by! Each building is nearing completion with drywall, painting tile install and flooring. Check out the rest of the updates for the next two weeks!
The Flats:
Building 6772: Complete drywall and ceilings. Continue painting, setting cabinets, doors and trim, shower tile install and hardwood flooring. Complete architectural metal panels, HVAC systems and hot water heaters. Continue site work for paving and sidewalks.
Building 6766: Complete drywall hang and finish. Continue painting, setting cabinets, doors and trim, shower and floor tile install. Begin hardwood flooring and continue architectural metal panels.
Building 6758: Continue hanging and finishing drywall, interior painting and framing soffits and drops. Continue MEPs in drop ceilings and begin architectural metal panels.
Building 6741: Continue hanging and finishing drywall. Begin interior painting, frame soffits and drops. Continue MEPs in drop ceilings and begin architectural metal panels.
Continue metal stud framing, stone and brick veneer, interior MEP rough-ins, air barrier and drywall prerock. Complete installing balcony doors.
PT/OT:
Waiting on Phase 2 start once ODH letter is received.
Finish drywall, install stone cap and begin bulletin #2 changes.
River’s Edge Café:
Begin underground plumbing.