Construction is moving swiftly on the expansion project at Friendship Village of Dublin. In the next two weeks, we will be completing exciting new renovations and finishing touches. Here is what you can expect:
The Flats:
Building 10: Start metal roof, continue stone and brick veneer, continue MEP rough-ins, complete curtain wall, continue dry-wall pre-rock.
Building 9: Start metal roof, continue stone veneer, continue MEP rough-ins, complete window installation, and complete curtain wall glazing.
Building 8: Complete roof shingles, continue MEP rough-ins, complete windows and continue curtain wall.
Building 7: Complete roof singles and continue MEP rough-ins.
Install gas service throughout.
Riverstone:
Pour level 4 North and continue CMU install.
PT/OT Area:
Begin bulletin 8 plumbing and finish metal stud framing.
Lobby/Offices:Complete a few items in the newly renovated and stunning lobby area
Bistro:
Dig and pour footers and start CMU foundation.