Completed Roofing, Framing and Our New Lobby!

Dig and pour footers and start CMU foundation

[Updated: August 2, 2018 | Published: February 8, 2017]

Construction is moving swiftly on the expansion project at Friendship Village of Dublin. In the next two weeks, we will be completing exciting new renovations and finishing touches. Here is what you can expect:

 

The Flats:

Building 10: Start metal roof, continue stone and brick veneer, continue MEP rough-ins, complete curtain wall, continue dry-wall pre-rock.Exterior view of building with roof placed

Building 9: Start metal roof, continue stone veneer, continue MEP rough-ins, complete window installation, and complete curtain wall glazing.

Building 8: Complete roof shingles, continue MEP rough-ins, complete windows and continue curtain wall.

Building 7: Complete roof singles and continue MEP rough-ins.

Install gas service throughout.

 

Construction site of building

 

Riverstone:

Pour level 4 North and continue CMU install.

 

 

bath tub in the middle of construction area

 

 

PT/OT Area:

Begin bulletin 8 plumbing and finish metal stud framing. 

 

 

Renovated lobby showcases furniture and fireplace

 

Lobby/Offices:Complete a few items in the newly renovated and stunning lobby area

 

 

Dig and pour footers and start CMU foundation

 

 

Bistro:

Dig and pour footers and start CMU foundation.

 

 

Download this update as a printable PDF.

News Categories

Get the Latest Email News

  • This field is for validation purposes and should be left unchanged.
Aa Aa Aa
September 18 Special Event: Caring for Aging Parents Click here for details and registration