The expansion project continues at Friendship Village of Dublin and we are so excited to share all of the exciting new updates with you this week. Here’s what we are working on in the next two weeks:
The Flats
Building 10: Start metal roof, continue stone and brick veneer, continue MEP rough-ins, complete curtain wall and continue hollow metal doorframe install.
Building 9: Start metal roof, continue stone veneer, continue MEP rough-ins and complete curtainwall glazing.
Building 8: Start metal roof, continue MEP rough-ins, continue curtain wall and frame punch-out.
Building 7: Start metal roof and continue MEP rough-ins.
Riverstone
Remove 4 North formwork
Continue prepping 4 South for pour on Friday 2/10 or Monday 2/13.
Continue CMU install

PT/OT area
Final plumbing inspection
Begin drywall work
Continue work on fire alarm
Lobby/Offices
Begin hanging drywall
Bistro
Continue CMU foundation
Slab pour week of 2/13