[Updated: August 1, 2018 | Published: August 18, 2017]
Our Flats buildings are getting final finishes and inspections are starting. The dining options are getting an update too, with The Bistro and River’s Edge Cafe getting started. Read more of our exciting updates over the next two weeks!
The Flats:
Building 6772: Begin cleaning and completing architect’s punch on the 4th and 5th floor. Continue finishes and trim. Install toilet and bath accessories. Start inspections.
Building 6766: Complete carpet install.Begin cleaning and completing architect’s punch on the 4th and 5th floor. Continue finishes and trim. Start inspections.
Building 6758: Continue interior painting. Complete countertops, trim and
doors, wood flooring, electrical fixtures and devices.
Building 6741: Continue interior painting. Complete countertops, trim and
doors, wood flooring, electrical fixtures and devices. Install asphalt paving
Riverstone:
Continue metal stud framing, EIFS at balconies, stone and
brick veneer on the west and south elevations. Continue Interior MEP rough ins, batt insulation north attic and drywall north attic. Start work on existing courtyard wall.
PT/OT:
Continue wall framing and MEP rough ins.
Bistro:
Final paint touch ups, permit update and final city approval.
River’s Edge Café:
Pour concrete slab on grade and pour precast topping slab.
Signalization:
Thermal striping (weather permitting).
Corridors Work:
Begin adding windows upon receipt of JMM’s sketch. Start prime painting and wood trim on the 4th floor. Start prime painting on the 3rd floor.
Art Studio Remodel:
HVAC rough inspection. Begin drywall hanging.