Drywall and Flooring at the Flats

Drywall and Flooring at the Flats

[Updated: August 1, 2018 | Published: July 28, 2017]

Most of the interior work on the flats is completed and we’re finishing the stairwells and corridors. The flats will be ready for move-in before we know it! Read about that and other expansion updates over the next two weeks.

Kitchen construction in the FlatsThe Flats:
Building 6772: Complete drywall, ceilings stairwells and shower tile install. Continue to finish painting, hardwood flooring and kitchen backsplashes. Complete architectural metal panels, countertop install, ceiling grid and HVAC systems trim. Continue sitework for paving and sidewalks and installing electric fixtures and devices.

Building 6766: Complete drywall hang and finish stairwells. Continue painting, doors and trim and shower and floor tile install. Begin hardwood flooring and countertops. Continue installing electrical fixtures and devices and architectural metal panels.

Building 6758: Complete hanging and finishing drywall in the stairwells and corridors. Continue interior painting and architectural metal panels. Begin cabinet installation

Building 6741: Complete hanging and finishing drywall in the stairwells and corridors. Continue interior painting and architectural metal panels.

Construction in riverstoneRiverstone:
Continue miscellaneous metal stud framing and RC channel. Complete installing balcony doors. Continue stone and brick veneer, interior MEP rough-ins, drywall pre-rock and installing secondary wire.


PT/OT
:
Waiting on Phase 2 start, anticipated start date of 7/31.

Bistro:
Continue painting, above ceiling MEPs and punchout.
River’s Edge Café:
Complete excavating for underground plumbing and installing pipe. Complete CMU up to 2nd floor bearing. Slab on grade prep and pour.

Signalization:
Asphalt patching and stripping. Start signal pedestal work.

Corridors Work:Construction in the arts-and-crafts room metal frame is up
Start wood base installation & ceiling grid on the 4th floor. Start framing of archways and fire calking on the 3rd floor.

Art Studio Remodel:
Complete soffit framing. Start electric and plumbing rough-ins.

News Categories

Get the Latest Email News

  • This field is for validation purposes and should be left unchanged.
Aa Aa Aa
September 18 Special Event: Caring for Aging Parents Click here for details and registration