Drywall, Insulation and Other Exciting Updates!

Outside view of the Flats

[Updated: August 10, 2018 | Published: April 21, 2017]

We have some exciting updates planned for the next couple of weeks! The Flats buildings are continuing to make progress with drywall and insulation. The B-Wing offices are ready for final inspection and will be ready for employees soon. Check out the other updates:

Inside view of flats hallway with ladders and toolsThe Flats:

Building 10: Continue drywall install, exterior soffit and fascia, lobby metal studs and MEPs post prerock. Begin interior soffit framing.

Building 9: Continue drywall hang and finish.

Building 8: Complete MEP rough-ins and stone and brick veneer. Begin Insulation.

Building 7: Continue MEP rough-ins, inspections and stone and brick veneer. Complete frame punchout.

 

Outside view of frame work of riverstone with two cranes in sightRiverstone:

Continue metal stud framing and hanging exterior fiberglass board. Continue setting trusses and sheathing roof. Begin north pan stairs. Continue garage level plumbing piping and continue through 1st floor. Remove scaffold around CMU south stairs.

Kitchen with appliances in place and white cabinets with silver hardware

 

PT/OT:

Complete punchlist items. Phase 1 complete.

 

 

Office with carpet in place with tools and a trash can in the middle
Offices (B-Wing)
:

Complete punchlist items, final inspections and cleaning.

Construction on the bistro

 

 

Bistro:

Continue stone veneer and demo at infill.

 

 

Cafe from the outside with dirt on the ground landscape has not been placed

 

 

River’s Edge Café:

Conduct kickoff meeting and begin footing work.

News Categories

Get the Latest Email News

  • This field is for validation purposes and should be left unchanged.
Aa Aa Aa
September 18 Special Event: Caring for Aging Parents Click here for details and registration