[Updated: August 10, 2018 | Published: April 21, 2017]
We have some exciting updates planned for the next couple of weeks! The Flats buildings are continuing to make progress with drywall and insulation. The B-Wing offices are ready for final inspection and will be ready for employees soon. Check out the other updates:
Building 10: Continue drywall install, exterior soffit and fascia, lobby metal studs and MEPs post prerock. Begin interior soffit framing.
Building 9: Continue drywall hang and finish.
Building 8: Complete MEP rough-ins and stone and brick veneer. Begin Insulation.
Building 7: Continue MEP rough-ins, inspections and stone and brick veneer. Complete frame punchout.
Riverstone:
Continue metal stud framing and hanging exterior fiberglass board. Continue setting trusses and sheathing roof. Begin north pan stairs. Continue garage level plumbing piping and continue through 1st floor. Remove scaffold around CMU south stairs.
PT/OT:
Complete punchlist items. Phase 1 complete.
Offices (B-Wing):
Complete punchlist items, final inspections and cleaning.
Bistro:
Continue stone veneer and demo at infill.
River’s Edge Café:
Conduct kickoff meeting and begin footing work.