[Updated: August 1, 2018 | Published: June 13, 2017]
The construction workers aren’t letting the heat slow them down! The flats are getting cabinets installed along with exterior items like gutters and downspouts – they will be ready for move in before we know it! Read more about what we have going on in the next two weeks.
Building 10: Continue gutters and downspouts, drywall and ceilings. Continue painting, setting cabinets, doors and trim. Continue shower tile install, architectural metal panels and setting unit furnaces. Begin site flatwork.
Building 9: Continue drywall hang and finish. Continue metal stud framing and painting. Start setting cabinets and continue doors and trim. Begin architectural metal panels.
Building 8: Continue hanging and finishing drywall. Begin paint prime. Continue framing soffits and drops.
Building 7: Complete stone and brick veneer. Continue hanging and finishing drywall.
Continue metal stud framing, window installation, curtain wall installation and stone veneer. Continue Interior MEP rough-ins, air barrier and drywall pre-rock. Complete trusses and sheathing at B-Wing connectors.
PT/OT:
Complete any open punchlist items.
Offices (B-Wing):
Complete any open punchlist items. Continue additional requested work.
Continue stone veneer. Pour topping slab. Start insulation and paint prime.
River’s Edge Café:
Pour footing. Begin installing CMU.