Exciting Dining Updates

Cafe almost complete shows outside of cafe

[Updated: August 1, 2018 | Published: June 13, 2017]

The construction workers aren’t letting the heat slow them down! The flats are getting cabinets installed along with exterior items like gutters and downspouts – they will be ready for move in before we know it! Read more about what we have going on in the next two weeks.

Kitchen in the Flats under constructionThe Flats:

Building 10: Continue gutters and downspouts, drywall and ceilings. Continue painting, setting cabinets, doors and trim. Continue shower tile install, architectural metal panels and setting unit furnaces. Begin site flatwork.

Building 9: Continue drywall hang and finish. Continue metal stud framing and painting. Start setting cabinets and continue doors and trim. Begin architectural metal panels.

Building 8: Continue hanging and finishing drywall. Begin paint prime. Continue framing soffits and drops.

Building 7: Complete stone and brick veneer. Continue hanging and finishing drywall.

Metal studded framing up in RiverstoneRiverstone:

Continue metal stud framing, window installation, curtain wall installation and stone veneer. Continue Interior MEP rough-ins, air barrier and drywall pre-rock. Complete trusses and sheathing at B-Wing connectors.

PT/OT:

Complete any open punchlist items.

Offices (B-Wing):

Complete any open punchlist items. Continue additional requested work.

Future bistro site under constructionBistro:

Continue stone veneer. Pour topping slab. Start insulation and paint prime.

River’s Edge Café:

Pour footing. Begin installing CMU.

News Categories

Get the Latest Email News

  • This field is for validation purposes and should be left unchanged.
Aa Aa Aa
September 18 Special Event: Caring for Aging Parents Click here for details and registration