[Updated: August 1, 2018 | Published: October 25, 2017]
The Flats residents have officially started moving in! The construction crew is hard at work finishing up the last minute details to ensure the move-in process goes smoothly. Read more about what we have planned for the next two weeks.
The Flats:
Flat 6772: Continue RCC punchlist and resident move-ins.
Flat 6766: Continue cleaning, RCC punchlist and resident move-ins.
Flat 6758: Continue interior painting, cleaning, RCC punchlist and resident move-ins.
Flat 6741: Continue interior painting, cleaning, RCC punchlist and begin resident move-ins.
Flat Site: Continue finish grading, landscaping and walk path asphalt.
Riverstone:
West soffit and fascia metal on-going. Continue brick on southwest and work on the south elevator. The duct shafts are continuing ongoing inspections. The 1st floor ceiling framing has been started along with the 2nd floor ceiling drywall. The 3rd floor is getting the walls primed and painted and the 4th floor RI is in progress.
PT/OT:
Begin drywall punch, set countertops and begin final coat of paint.
Friendship Center / River’s Edge Café:
Continue MEP rough ins, continue framing and set trusses.
Corridors Work:
4th floor begin dropping in ceiling tile, continue painting and continue flooring. 3rd floor begin dropping in ceiling tile, continue painting and continue flooring. 2nd floor continue removing and replacing trim. 1st floor continue skimming walls and fire caulking
Arts Studio Remodel:
Begin paint priming and installing trim and doors. Continue prepping for kiln.