The Flats are getting major updates both structurally and visually over the next two weeks. Each Flats apartment will have a completed metal roof and along with insulation and drywall being started. Check out the other updates:
The Flats
Building 10: Complete Metal Roof. Continue stone and brick veneer, MEP rough-ins, building insulation, drywall install and exterior soffit.
Building 9: Complete Metal Roof. Continue stone and brick veneer, MEP rough-ins, curtainwall glazing, MEP inspections and building insulation. Begin Drywall.
Building 8: Complete Metal Roof. Continue MEP rough-ins, curtain wall, frame punchout and stone and brick veneer.
Building 7: Complete Metal Roof. Continue MEP rough-ins, curtain wall, frame punchout and stone and brick veneer.
Riverstone
Continue exterior stud framing and hanging exterior fiberglass board, setting trusses setting precast balconies and garage level plumbing piping. Begin electrical conduit in garage.
PT/OT
Install flooring, complete final coat of paint and perform construction clean.
Offices (B-Wing)
Begin casework and molding.
Bistro
Install temporary partitions and shoring. Set precast roof lid.