Flats Roofing Completed and Other Expansion Updates!

Cafe almost complete shows outside of cafe

[Updated: August 2, 2018 | Published: April 3, 2017]

The Flats are getting major updates both structurally and visually over the next two weeks. Each Flats apartment will have a completed metal roof and along with insulation and drywall being started. Check out the other updates:

View of construction progress on flats

The Flats

Building 10: Complete Metal Roof. Continue stone and brick veneer, MEP rough-ins, building insulation, drywall install and exterior soffit.

Building 9: Complete Metal Roof. Continue stone and brick veneer, MEP rough-ins, curtainwall glazing, MEP inspections and building insulation. Begin Drywall.

Building 8: Complete Metal Roof. Continue MEP rough-ins, curtain wall, frame punchout and stone and brick veneer.

Building 7: Complete Metal Roof. Continue MEP rough-ins, curtain wall, frame punchout and stone and brick veneer.

Exterior stud framing of riverstone

 

Riverstone

Continue exterior stud framing and hanging exterior fiberglass board, setting trusses setting precast balconies and garage level plumbing piping. Begin electrical conduit in garage.

 

Construction worker on the interior of a building


PT/OT

Install flooring, complete final coat of paint and perform construction clean.

 

Inside of office with doors waiting for crown molding

Offices (B-Wing)

Begin casework and molding.

 

bistro under construction outside view with blue sheets covering framing

 

Bistro

Install temporary partitions and shoring. Set precast roof lid.

News Categories

Get the Latest Email News

  • This field is for validation purposes and should be left unchanged.
Aa Aa Aa
THREE Fall Events in October and November! Click here for details and registration