[Updated: August 1, 2018 | Published: June 29, 2017]
The flats are coming along with more drywall, painting and cabinets! Check out the rest of the updates coming in the next two weeks.
The Flats:
Building 6772: Complete drywall, ceilings, painting and setting cabinets, doors and trim. Continue shower tile install and hardwood flooring. Complete architectural metal panels, setting unit furnaces and hot water heaters. Continue site work for paving and sidewalks.
Building 6766: Complete drywall hang and finish, painting, and setting cabinets, doors and trim. Continue shower and floor tile install. Begin hardwood flooring and architectural metal panels.
Building 6758: Continue hanging and finishing drywall, interior painting, framing soffits and drops. Continue MEPs in drop ceilings.
Building 6741: Continue hanging and finishing drywall and MEPs in drop ceilings. Begin interior painting and frame soffits and drops.
Riverstone:
Continue metal stud framing, installing balcony doors, stone and brick veneer and interior MEP rough-ins. Continue air barrier, North and South stair roof and drywall pre-rock.
Waiting on Phase 2 start after ODH inspection of Phase 1.
Offices (B-Wing):
Complete any open punchlist items.
Bistro:
Completed stone veneer, except for cooler construction opening. Continue roughing in and inspecting MEPs. Awaiting bulletin #2 approval. Installed hydrant at roof patio.
River’s Edge Café:
Completed foundation CMU and backfilled around foundation.