Our biggest news this week is that the foundation at the flats has been poured, but the work doesn’t stop there. Here’s what we have planned for the next two weeks:
Sitework & Utilities
Complete Boulder outcroppings wall
Garages:
Demolish the old garages, July 5th
Utility Pump House/Entry Feature
Finish valve installation
Flats
Building 6772: Continue Foundation CMU Walls, Backfill of perimeter walls, Electrical underground rough-in, Slab on Grade
Building 6766: Continue Foundation CMU walls, Plumbing underground rough-in
Building 6758: Continue CMU Foundation walls, Install plumbing sump pit
Building 6741: CMU Foundation Walls
Riverstone
Continue B-Wing North Exterior Demolition, complete 7/1/16.
Start B-Wing South Exterior Demolition, Start 7/6/16