Our biggest news this week is that the foundation at the flats has been poured, but the work doesn’t stop there. Here’s what we have planned for the next two weeks:

 

Sitework & Utilities

Complete Boulder outcroppings wall

Garages:

Demolish the old garages, July 5th

 

Utility Pump House/Entry Feature

Finish valve installation

 

Flats

Building 6772: Continue Foundation CMU Walls, Backfill of perimeter walls, Electrical underground rough-in, Slab on Grade

Building 6766: Continue Foundation CMU walls, Plumbing underground rough-in

Building 6758: Continue CMU Foundation walls, Install plumbing sump pit

Building 6741: CMU Foundation Walls

 

Riverstone

Continue B-Wing North Exterior Demolition, complete 7/1/16.

Start B-Wing South Exterior Demolition, Start 7/6/16

Retention Wall, Mobilize Tuesday 7/5/16, Start 7/6/16

 

Download as printable PDF.

Construction site where workers are laying foundation

News Categories

Get the Latest Email News

  • This field is for validation purposes and should be left unchanged.
Aa Aa Aa
September 18 Special Event: Caring for Aging Parents Click here for details and registration