It has been a busy few weeks for our construction crews as major progress has been made on the Flats and Riverstone apartments. Stay tuned for more updates as Winter comes to an end and Spring begins!
The Flats:
Building 10: Complete Metal Roof. Continue stone and brick veneer. Continue MEP Rough-ins. Complete Curtain Wall. Continue Building Insulation. Continue Drywall Install.
Building 9: Complete Metal Roof. Continue stone and brick veneer. Continue MEP Rough-ins. Complete Curtainwall glazing. MEP Inspections. Begin Building Insulation.
Building 8: Complete Metal Roof. Continue MEP Rough-ins. Complete Curtain Wall. Frame Punchout. Continue Stone Veneer.
Building 7: Complete Metal Roof. Continue MEP Rough-ins. Complete Curtain Wall. Frame Punchout.
Riverstone:
Continue exterior stud framing and hanging exterior fiberglass board.
Continue setting trusses.
Continue CMU install on South stairs.
Continue garage level plumbing piping. Set precast balconies.
PT/OT:
Continue hanging ceiling tile grid. MEP finishes above ceiling.
Install Doors and hardware. Install Free Step System.
Complete final coat of paint. Install flooring.
Continue dampers and fire alarm.
Offices (B-Wing):
Paint prime. Install trim.
Bistro:
Measure for precast lid.
Complete air barrier install (weather dependent).