[Updated: August 3, 2018 | Published: February 22, 2017]
The next two weeks will be full of advancements for the Friendship Village of Dublin expansion project. Here is what you can expect to see:
The Flats
Building 10: Start metal roof, continue stone and brick veneer, continue MEP rough-ins, complete curtain wall, continue hollow metal doorframe installation and begin pre-rock.
Building 9: Start metal roof, continue stone veneer, continueMEP rough-ins and complete curtainwall glazing.
Building 8: Start metal roof, continue MEP rough-ins, continue curtain wall and frame punchout.
Building 7: Start metal roof, continue MEP rough-ins and start curtain wall.
Riverstone
Stress 4 South tendons
Remove all formwork from site
Continue CMU installation
Begin exterior stud framing
PT/OT
Begin drywall work
Complete work on fire alarm
Lobby/Offices
Begin hanging drywall
Bistro
Pour Bistro infill footing