[Updated: April 20, 2018 | Published: July 14, 2016]
The walls are coming down and Riverside is one step closer to being completed. We’ve also continued making progress on the Stone Wall installation for the Utility Pump House. Check out what else is going on:
Sitework & Utilities
Complete Boulder outcroppings along sidewalk to Villas
Garages
Re-grade and compact parking lot
Utility Pump House/Entry Feature
Stone wall installation in progress
Pavilion
Boulders behind the sidewalk started
Install cut stone cap and complete the carpentry trim work
Install Roof 7/25/16
Flats
Building 6772: Continue CMU walls, Slab on Grade, 7/25/16 set precast deck
Building 6766: Continue CMU walls, 7/25/16 set precast deck
Building 6758: Continue CMU walls
Building 6741: Continue CMU walls
Riverstone
Drill Rig – Continue B-Wing North Retaining wall
Continue B-Wing South exterior demolition
Drill Rig to install columns for B-Wing South retention wall
Continue utility relocation and building pad excavation