Offices Nearing Completion and Other Construction News!

Office almost complete with hardwood floors

[Updated: August 1, 2018 | Published: April 12, 2017]

We have some exciting expansion updates over the next two weeks! The B-Wing offices will be getting a final coat of paint and floors. The Bistro and River’s Edge Cafe will be ready for dining before we know it. Check out all of the updates: 

The Flats:

Building 10: Continue drywall install and exterior soffit and fascia.

flatsBuilding 9: Complete metal roof, stone and brick veneer. Continue MEP Rough-ins and MEP inspections. Begin Drywall.

Building 8: Complete metal roof and MEP rough inspections. Continue MEP Rough-ins, frame punchout and brick veneer.

Building 7: Complete metal roof, curtain wall and frame punchout. Continue MEP rough-ins and stone and brick veneer.

riverstoneRiverstone:

Continue exterior stud framing and hanging exterior fiberglass board, setting trusses, setting precast balconies and garage level plumbing piping. Begin 1st floor and electrical conduit in garage. Top out CMU south stairs.

PT/OT:ptot

Install flooring. Complete final coat of paint. Perform construction clean and punchlist items.

 

Offices (B-Wing):offices

Complete final coat of paint. Install Flooring. General punchout.

 

bistro
Bistro
:

Install shoring, finish precast lid and begin installing exterior veneer.

 

River’s Edge Café:

Complete install temporary partition walls and fencing at Door A. Start Demolition.

News Categories

Get the Latest Email News

  • This field is for validation purposes and should be left unchanged.
Aa Aa Aa
September 18 Special Event: Caring for Aging Parents Click here for details and registration