[Updated: August 2, 2018 | Published: May 5, 2017]
The rainy weather hasn’t stopped our crews from making big construction progress. The offices and PT/OT units are almost completely ready to use! Read what we have going on in the next couple of weeks:
Building 10: Continue drywall install, exterior soffit and fascia. Continue MEPs post prerock and interior dropped ceilings. Hang drywall dropped ceilings. Start painting on the 4th floor.
Building 9: Continue drywall hang and finish and metal stud framing.
Building 8: Continue stone and brick veneer and building insulation. Complete framing and insulation inspections. Start drywall.
Building 7: Continue stone and brick veneer. Begin building wall insulation.
Continue metal stud framing and hanging exterior fiberglass board. Continue setting trusses and sheathing roof. Continue asphalt shingles. Begin setting and pouring concrete treads at north stairs. Continue garage level plumbing piping and continue through the building. Continue stone veneer and interior MEP rough ins.
PT/OT:
Complete any open punchlist items.
Offices (B-Wing):
Complete any open punchlist items.
Bistro:
Continue stone veneer, demo at infill and community center cafe. We are currently waiting for permitting from the city to start footings.