[Updated: April 20, 2018 | Published: May 26, 2017]
While the offices and PT/OT suites are ready for move-in, there are other exciting updates around the community. Check out what we have planned for the next two weeks!
Building 10: Continue exterior soffit and fascia, drywall and ceilings. Continue painting, setting cabinets, doors and trim.
Building 9: Continue drywall hang and finish. Continue metal stud framing and painting. Start setting cabinets. Continue doors and trim.
Building 8: Continue hanging and finishing drywall.
Building 7: Continue stone and brick veneer. Continue hanging and finishing drywall.
Continue metal stud framing and soffit framing. Continue window installation, stone veneer and interior MEP rough-ins. Continue air barrier. Set trusses and sheathing at B-Wing connectors.
PT/OT:
Complete any open punch-list items.
Offices (B-Wing):
Complete any open punch-list items. Continue additional requested work.
Continue stone veneer, set roof drains and pour topping slab.
River’s Edge Café:
Start foundations pending receipt of building permit.